引用本文: | 黄晓明,黄志华,张华娇,等.变电站整站二次设备就地化及运维方案研究[J].电力系统保护与控制,2019,47(5):173-178.[点击复制] |
HUANG Xiaoming,HUANG Zhihua,ZHANG Huajiao,et al.Research on the localization and maintenance scheme of secondary equipment in substation[J].Power System Protection and Control,2019,47(5):173-178[点击复制] |
|
摘要: |
结合目前就地化保护研究和试运行的现状,提出了一种变电站整站二次设备就地化应用、运行和维护方案。首先分析了变电站保护、自动化等专业的具体业务需求,统一整站技术风格,提出了各业务二次设备就地化解决方案,构建整站就地化二次系统。并在此基础上探索了“工厂化调试”和“更换式检修”创新运维手段。整站二次设备就地化后,变电站整体保护功能性能提升,自动化功能高度集成。“工厂化调试”和“更换式检修”后变电站二次设备的调试和运维工作更方便、更高效。 |
关键词: 就地化保护 基本测控 辅助测控 二次设备整站就地化 工厂化调试 更换式检修 |
DOI:10.7667/PSPC180364 |
投稿时间:2018-04-02修订日期:2018-06-13 |
基金项目:国网浙江省电力公司科技项目资助(5211UZ16000A) |
|
Research on the localization and maintenance scheme of secondary equipment in substation |
HUANG Xiaoming,HUANG Zhihua,ZHANG Huajiao,LIU Ying,CHEN Yongwei,DING Hao |
(Huzhou Power Supply Company, State Grid Zhejiang Electric Power Company, Huzhou 313000, China;Beijing Sifang Automation Co., Ltd., Beijing 100085, China) |
Abstract: |
Combined with the current situation of research and trial operation of local installation protection, a local installation application and operation and maintenance solution of entire substation is put forward. First, the specific business requirements of substation protection and automation are analyzed. Then the technical style of the whole station is unified, the secondary equipment localization solution for each business is put forward, and the whole substation's local installation secondary protection and control system is constructed. On this basis, this paper explores the local secondary equipment “factory debugging” and “replacement maintenance” operation means. After local installation secondary equipment solution of entire substation, the substation's overall protection function is improved and the automation function is highly integrated. The “factory debugging” and “replacement maintenance” operation means is more convenient and efficient for the debugging work and maintenance work in substation. This work is supported by Science and Technology Project of State Grid Zhejiang Electric Power Company (No. 5211UZ16000A). |
Key words: local installation protection basic measurement and control auxiliary measurement and control substation secondary protection and control equipment localized application factory debugging replacement maintenance |