引用本文: | 罗治强,杨军峰,王其祥,胡林献.应对大功率缺失的分-省协调实时调度模型[J].电力系统保护与控制,2019,47(12):132-137.[点击复制] |
LUO Zhiqiang,YANG Junfeng,WANG Qixiang,HU Linxian.Region-province coordinated real-time dispatch model considering large-scale power loss[J].Power System Protection and Control,2019,47(12):132-137[点击复制] |
|
摘要: |
针对大功率交直流联络线故障将导致受端电网大规模功率缺失,而省域电网内部分机组由省级电网调度,另一部分由区域分中心调度等问题,研究分-省两级电网调度中心实时发电计划协调调整策略。首先建立了省调机组/直调机组有功调整量分配模型和出力跟踪校验模型。针对省调机组/直调机组可能无法完全跟踪分配到的有功调整量的情况,进一步提出了省调机组/直调机组有功协调策略及出力校正模型,形成了一套适用于省域电网大功率缺失场景的省调机组/直调机组实时发电计划协调编制方法。仿真结果表明,与常规实时调度方法相比,该方法有助于快速恢复省域电网大功率缺失后的有功平衡。 |
关键词: 分-省协调 实时调度 大功率缺失 省调机组 直调机组 |
DOI:10.7667/PSPC20191216 |
投稿时间:2018-07-07修订日期:2018-10-01 |
基金项目:国家电网公司科技项目(5442dz180019)“全局计划决策与现货市场核心技术研究与应用” |
|
Region-province coordinated real-time dispatch model considering large-scale power loss |
LUO Zhiqiang,YANG Junfeng,WANG Qixiang,HU Linxian |
(National Electric Power Dispatching and Control Center, Beijing 100031, China;State Grid Luoyang Power Supply Company, Luoyang 471000, China;School of Electrical Engineering & Automation, Harbin Institute of Technology, Harbin 150001, China) |
Abstract: |
Failure of high-power AC/DC tie-line will lead to large-scale power loss in the receiving-end power grid, and a part of the provincial units are dispatched by the provincial power grid (P-Units), the other part is dispatched by the regional grid (R-Units). In view of the above problems, the coordinated adjustment strategy of real-time generation plan for regional and provincial dispatching units is studied. Firstly, the models for the allocation of active power adjustment and output tracking between P-Units and R-Units are constructed. For the cases that P-Units or R-Units might not be able to track the allocated active power adjustment, a coordination strategy for active power of P-Units and R-Units is proposed, followed by an output correction model. Together, a set of real-time scheduling methods coordinated P-Units and R-Units which are suitable for provincial power grid under large power loss are formed. Simulation result shows that compared with conventional real-time scheduling method, the proposed method is conducive to fast recovery of provincial grid active power balance after large-scale power loss. This work is supported by Science & Technology Project of State Grid Corporation of China (No. 5442dz180019) “Research and Application of Core Technology in Global Planning Decision and Spot Market” . |
Key words: region-province coordination real-time dispatch large-scale power loss provincial dispatching units regional dispatching units |